		ARM WG 2 Task plan
Meaning of symbols for sessions :
| v | + | x | > | < | 
| Scheduled | Progressed | Not progressed | Finalised | On hold | 
| Standard | Topic Area | Task no. | Task | 17 | 18 | 19 | 20 | 21 | 22 | 23 | Status (Text) | Status (Colour) | Task leader | Remarks | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Leading : ARM | ||||||||||||||
| Leading : ARM WG 2 | ||||||||||||||
| S1010 Marine Aids to Navigation Planning And Service Requirements | S1010.4 Risk management | 1.4.3 | New guideline in support of the recommendation on Cyber security | v | > | Approved by Council - Complete | Finished | Martijn Ebben | ||||||
| S1020 Marine Aids to Navigation Design and Delivery | S1020.2 Design, Implementation & Maintenance | 2.2.3 | Develop an IALA recommendation and guideline on the Harmonized National Waterway Concept | v | v | > | Finished | Amilynn Adams | The recomendation and guideline was approved bij council and published December 2024 | |||||
| S1050 Training and Certification | S1050.2 Accreditation, competency certification and revalidation | 5.2.1 | Develop a model course on AtoN Cyber Security arrangements | > | Finished | |||||||||
| S1070 Information Services | S1070.1 Data models and data encoding | 7.1.3 | New Guideline on Operational considerations for S-200 (S-201 AtoN information and S-230 Application Specific Messages) | v | v | v | v | v | v | On track | Sewoong Oh | |||
| 7.1.4 | Continue development on S-201, specifically on Maintenance, data validation, and harmonization with S-125, S-124, and S-101 | v | v | v | v | v | v | v | Completed the S-201 to a edition 2.0. | On track | Sewoong Oh | Work was completed at ARM20. S-201 and acompanying files wil be up for review by the IALA members until mid May before it will be send to Council for approval.. | ||
| 7.1.5 | Coordinate with IHO on implementation of IALA PS into S-98 | v | v | v | v | v | v | v | Not started | Peter Hooijmans | ||||
| 7.1.6 | Continue development on S-125 in coordination with IHO NIPWG | v | v | v | v | v | v | v | Finalized edition 1.0 | On track | Sewoong Oh | Ongoing work in cooperation with IHO S-125 TG. | ||
| 7.1.8 | Review Guideline G1106 on producing an IALA S-200 series Product Specification | v | v | v | > | Finished | Peter Hooijmans | |||||||
| 7.1.10 | Monitor the development of the test & validation tool | v | v | v | v | v | v | v | On track | Sewoong Oh | ||||
| 7.1.11 | Develop, implement and execute procedures for IALA to add, maintain and harmonize items to the IHO S-100 feature concept dictionary(FCD). | v | v | v | v | v | v | v | On track | Sewoong Oh | ||||
| 7.1.12 | Create S-200 Implementation Plan, following similar S-100 Implementation Strategy and/or Roadmap | v | v | x | v | v | On track | Peter Hooijmans | No work was done at ARM20 | |||||
| 7.1.15 | Review Guideline G1159 on ship reporting from the shore side perspective | > | v | v | v | Finished | Peter Hooijmans | The working group deemed no work was necessary on the revision of this guideline and regards this task as finished. | ||||||
| 7.1.2 | Contribute to the standardization efforts with respect of the requirements of the S-100 domain experts | v | v | v | v | v | v | v | On track | Peter Hooijmans | ||||
| 7.1.9 | Coordinate Committee support and submissions for IALA representation at IHO working groups in cooperation with Secretariat (HSSC, S-100WG, NIPWG) | v | v | v | v | v | v | v | On track | Peter Hooijmans | ||||
| 7.1.1 | Develop guidance on Digital Fairway | v | v | v | v | Not started | Peter Hooijmans | |||||||
| 7.1.7 | Continue development on MRN documentation, considering inputs from IALA Secretariat, other committees, or others as needed | v | v | v | v | v | v | v | On track | Martijn Ebben | Intersessional work wil be planned for this task. As requested by the other committees. | |||
| S1070.2 Data exchange systems | 7.1.14 | Development of technical service specifications for the provision of AtoN information | v | v | v | v | v | v | v | On track | Nikolaos Vastardis | |||
| S1070.3 Terminology, symboly and portrayal | 7.1.13 | Develop guidance on the symbology and portrayal of AtoN for other use than navigational charting | v | v | v | v | v | v | v | On track | Sewoong Oh | |||