ENG Committee Task plan
If you want to access the work plan of each working group you check it by clicking one of the button below. Assigning task numbers to committees and working groups permits to check easier tasks related and assigned between all working groups and committees.
Meaning of symbols for sessions :
v | + | x | > | < |
Scheduled | Progressed | Not progressed | Finalised | On hold |
Standard | Topic Area | Task no. | Task | 17 | 18 | 19 | 20 | 21 | 22 | 23 | Status (Text) | Status (Colour) | Task leader | Remarks |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Leading : ENG | ||||||||||||||
S1010 Marine Aids to Navigation Planning And Service Requirements | S1010.2 Aids to Navigation planning | 1.2.2 | Review relevant sections of the NAVGUIDE |
Not started
|
||||||||||
Leading : ENG WG 1 | ||||||||||||||
S1010 Marine Aids to Navigation Planning And Service Requirements | S1010.1 Obligations and regulatory compilance | 1.1.1 | Consider developing guidance on the certification of technical equipment, information systems and technical infrastructure related to MASS in the domain of IALA |
Not started
|
||||||||||
S1010.2 Aids to Navigation planning | 1.2.1 | Compile new Guideline on AtoN Tender requirementsand specification - Led by ARM with ENG support. | + | x | Complete |
Finished
|
Aw Eng Soon | |||||||
1.2.3 | Develop guidance on the provision of Marine AtoN for autonomous vehicle/vessel operations (Maritime Autonomous Surface Ship, MASS). |
Not started
|
||||||||||||
S1010.4 Risk management | 1.4.1 | Develop guidance on cyber security for Marine AtoN |
Finished
|
|||||||||||
S1020 Marine Aids to Navigation Design and Delivery | S1020.1 Aids to Navigation signalling | 2.1.1 | Update G1043 Light sources used in visual AtoN | v | v | v |
Not started
|
Lingyan Wang | ||||||
2.1.2 | Update G1048 LED technologies and their use in signal lights | v | v | v |
Not started
|
Lingyan Wang | ||||||||
2.1.3 | Develop guideline on Port Traffic Signals | ÷ | ÷ | ÷ | ÷ | ÷ | ÷ | ÷ |
Not started
|
Lingyan Wang | ||||
2.1.4 | Update R0112 Leading lights | v | + | + | + | v |
On track
|
Sarah Robinson | ||||||
2.1.5 | Update G1061 Light application illumination of structures | v | v |
Not started
|
Lingyan Wang | |||||||||
S1020.2 Design, Implementation & Maintenance | 2.1.6 | Update R0203(E200-3) | + | + | + | v | v | This task is on-gonging since ENG17. |
On track
|
Lingyan Wang | ||||
2.2.3 | Update G1041 Sector Lights | v | v |
Not started
|
Link Powell | |||||||||
2.2.4 | Update G1037 Data collection for AtoN performance calculation | + | x | v | In Progress |
Delayed
|
TBD | |||||||
2.2.5 | Update G1077 Maintenance of AtoN | v | v | > | Complete |
Finished
|
Chris Scully | |||||||
2.2.6 | Develop Guideline on complimentary use of AtoN | v | v | v | v |
On track
|
Cecille | |||||||
2.2.7 | Update and Amalgamate the Guidelines G1108,G1175 and G1136 | v | v | > | Complete |
Finished
|
Mariano | |||||||
2.2.8 | Update G1165 on Sustainable Structural Design |
Not started
|
Sarah Robinson | |||||||||||
S1020.3 Floating Aids to Navigation | 2.3.2 | Creating an overview guidance on floating AtoN | + | + | > | > | Complete |
Finished
|
Gillian Burns | |||||
2.3.3 | Update Recommendation R0107 (E-107) Moorings for floating AtoN | x | v | Additional Session |
Delayed
|
Pierre-Luc Delage | ||||||||
2.3.4 | Update G1066 Design of floating AtoN moorings | + | + | + | + | v | Additional Session |
Delayed
|
Pierre-Luc Delage | |||||
S1020.4 Environment and sustainability | 2.4.1 | Review and update as necessary G1036, the Green Guide | v |
Not started
|
||||||||||
2.4.2 | Guidance on through life environmental impact | v |
Not started
|
|||||||||||
S1020.3 Floating Aids to Navigation | 2.5.1 | Develop guidance on floating AtoN maintenance | + | + | v | On Track |
On track
|
Philippe Renaudin | ||||||
S1050 Training and Certification | S1050.1 Training and assessment | 5.1.1 | WWA lesson plans to review |
Not started
|
||||||||||
5.1.2 | Training in implementation of digital solutions (data analytics & maritime informatics) |
Not started
|
||||||||||||
S1060 Digital Communication Technologies | S1060.3 Harmonised maritime connectivity | 6.3.1 | Update G1008 Remote control and monitoring of AtoN | v | v | v |
Not started
|
Jonas Lindberg | ||||||
6.3.2 | Harmonised IoT Protocol for Visual AtoN | + | + | + | > |
On track
|
Jonas Lindberg | |||||||
Leading : ENG WG 2 | ||||||||||||||
S1030 Radionavigation Services | S1030.1 Satellite positioning and timing | 3.1.1 | Develop guidance on timing and synchronization | x | x | + | v | v |
Not started
|
Stefan Gewies | ||||
3.1.2 | WWRNP review | < | < | < | < | v | v |
On track
|
Jeffrey van Gils | |||||
S1030.2 Terrestrial positioning and timing | 3.2.1 | R-Mode development | + | + | + | v | v | v | v |
On track
|
Stefan Gewies | |||
3.2.2 | Develop the Recommendation and Guideline on R-Mode implementation (MF & VDES) | v | v | v |
On track
|
Stefan Gewies | ||||||||
3.2.3 | Develop the Recommendation for the Coordination for Group Repetition Intervals (GRI) | v | v | v |
Not started
|
Jeffrey van Gils | ||||||||
S1030.3 Augmentation services | 3.3.1 | Augmentation systems | + | + | v | v | v | v |
On track
|
José-Luis Martin | ||||
3.3.2 | High accuracy positioning systems | + | + | + | v | v | v | v |
On track
|
Sun Qian | ||||
3.3.3 | Develop Guideline on how to implement SBAS within VDES(ASM-VDE)/AIS | + | v | v | v |
Not started
|
José-Luis Martin | |||||||
3.3.4 | Develop a recommendation on SBAS services | v | v | v |
Not started
|
José-Luis Martin | ||||||||
S1030.4 Racon and Radar positioning | 3.4.1 | Radar & Enhanced Racon positioning | + | + | + | + | v | v | v |
On track
|
Paul Mueller | |||
3.4.2 | IMO liaison on Racon | + | > |
Finished
|
Paul Mueller |
ENG19-9.2.2.3 Liaison note to IMO on Enhanced Radar Positioning Systems |
||||||||
3.4.3 | Modify R0101 to recommendation and create new Guideline | + | v | v | v |
On track
|
Paul Mueller | |||||||
3.4.4 | Modify R0146 to a recommendation | + | + | v | v | v |
On track
|
Paul Mueller | ||||||
3.4.5 | Update G1010 Racon Range Performance | v | v | v |
Not started
|
Paul Mueller | ||||||||
S1070 Information Services | S1070.1 Data models and data encoding | 7.1.1 | S-200 PNT Product Specification | + | + | + | + | v | v | v |
On track
|
Younghoon Han | ||
7.1.2 | Develop S-200 product specification PNT Station almanac | v | v | v |
Not started
|
Younghoon Han | ||||||||
7.1.3 | Develop S-200 product specification PNT grid data | v | v | v |
Not started
|
Younghoon Han | ||||||||
No Standards | No Standards | 8.1.1 | PNT technology review | + | + | + | + | v | v | v |
On track
|
Jeffrey van Gils | ||
Leading : ENG WG 3 | ||||||||||||||
S1020 Marine Aids to Navigation Design and Delivery | S1020.6 Heritage & Culture | 2.6.1 | Maintain the Heritage web page on the IALA website | + | + | + | + | v | v | v |
On track
|
Gillian Burns | ||
2.6.2 | Develop Guidance on modern equipment in traditional lighthouses | + | + | + | + | v | v |
On track
|
Sarah-Jane LAKSHMAN | |||||
2.6.3 | Heritage Lighthouse of the Year award | + | + | + | + | v | v | v |
On track
|
Peter HILL | ||||
2.6.4 | Write the Heritage lecture for the WWA L1.1 AtoN Manager course | + | + | + | x | v | v | v |
On track
|
Ke RAXUAN | ||||
2.6.5 | Review of G1080 The Selection and Display of Heritage Artefacts | + | + | x | + | v | v |
On track
|
Jiwon SIM | |||||
2.6.5.b | Review Guideline G1093 Ed.1 The Management of Surplus Lighthouse Property, Dec 2012 | + | + | > | v | v | v |
Finished
|
Naehyuk Yoo | |||||
2.6.6 | Update G1063 Agreement for complementary use of lighthouses | + | + | + | + | v |
On track
|
Juan LIU | ||||||
2.6.7 | Review Guidelines 1074 and 1075 on Branding, Business plans for content and relevance | + | + | + | + | v |
On track
|
Zhenyu GUO | ||||||
2.6.8 | Review of R1005 Conserving the Built Heritage of Lighthouses and other Aids to Navigation | > |
Finished
|
Peter Hill |